Tarnow
Rated power: 2.05 MW
Wind Class: IEC 2a
Hub height: 100 m
Tower: Tubular Tower
Rotor diameter: 93 m
Date of commissioning: 30.11.2011
Av. annual yield: 5,142,319 kWh
Invest: approx. 5.000.000 €
USP: W2E’s first 2 MW prototype with Bachmann electronics controller
Project developer: Kloss New Energy GmbH
Financing Bank: Deutsche Kreditbank (DKB)
Kankel I
Rated power: 3.00 MW
Wind Class: IEC 2a
Hub height: 100 m
Tower: Tubular Tower
Rotor diameter: 120 m
Date of commissioning: 21.11.2013
Av. annual yield: 9,040,616 kWh
Invest: approx. 6.400.000 €
USP: W2E’s first 3 MW prototype; First ever used Winergy HybridDrive
Project developer: Kloss New Energy GmbH
Financing Bank: OstseeSparkasse Rostock
Kankel II
Rated power: 2.05 MW
Wind Class: IEC 3a
Hub height: 100 m
Tower: Tubular Tower
Rotor diameter: 100 m
Date of commissioning: 13.01.2014
Av. annual yield: 5,855,424 kWh
Invest: approx. 5.000.000 €
USP: W2E’s first 2 MW prototype with 100 m rotor diameter
Project developer: Kloss New Energy GmbH
Financing Bank: OstseeSparkasse Rostock
Kankel III
Rated power: 3.00 MW
Wind Class: IEC 2a
Hub height: 90 m
Tower: Tubular Tower
Rotor diameter: 120 m
Date of commissioning: 01.10.2014
Av. annual yield: 8,487,818 kWh
Invest: approx. 6.200.000 €
USP: W2E’s second 3 MW prototype
Project developer: Kloss New Energy GmbH
Financing Bank: OstseeSparkasse Rostock